9/20/2011

ERCOT Board Recommends Approval of ETT Proposed Transmission Line from Laredo into Rio Grande Valley

AUSTIN, TEXAS, Sept. 20, 2011 – The Electric Reliability Council of Texas (ERCOT) Board of Directors today endorsed and deemed “critical to reliability” a 345-kilovolt (kV) transmission project proposed by Electric Transmission Texas LLC (ETT) from the Laredo area into the Lower Rio Grande Valley.   ETT is a joint venture between subsidiaries of American Electric Power (NYSE: AEP) and MidAmerican Energy Holdings Company.   

ETT’s proposed transmission project includes construction of approximately 163 miles of 345-kV transmission lines that will connect ETT’s Lobo Substation near Laredo with substations north of Edinburg.   The cost of the project is estimated at approximately $300 million.  The ERCOT board recommendation also endorsed the need for AEP Texas to reconductor two existing 345-kv lines and upgrade substation facilities at an additional anticipated cost of $225 million. 

“The endorsement from the ERCOT board clearly establishes the need for this transmission project and paves the way for a Certificate of Convenience and Necessity (CCN) application from the Public Utility Commission of Texas (PUCT),” said ETT President Calvin Crowder.  “Currently, there are only two 345-kV transmission lines serving the Valley.  Both of the existing lines import power from the Corpus Christi area and run parallel to the Gulf Coast, which means both are vulnerable to hurricanes and other severe weather.  The import capacity of these lines is limited, and the ability to schedule maintenance often can be a problem.”  

The need for transmission improvements was reinforced during the February rolling outages throughout the state.  On the morning of Feb. 2, ERCOT called for firm load to be shed across the grid.  The AEP Texas share of the load shed was 380 MW.  After the resumption of normal activities, the Valley continued to face the possibility of outages due to severe weather.  On the evening of Feb. 3, AEP Texas shed 300 MW of load in the Valley as a result of the loss of a generator and transmission import limitations.   

Construction of the line also should further improve transmission reliability in the Laredo area.  

ETT anticipates filing a CCN application from the PUCT in 2012 with completion of the project envisioned for 2016.  ETT will develop potential routes and conduct environmental studies prior to scheduling open houses to discuss the project with landowners.

 ETT acquires, constructs, owns and operates transmission facilities within the ERCOT, primarily in and around the AEP Texas Central Company and AEP Texas North Company service territories.

AEP, headquartered in Columbus, Ohio, is one of the largest electric utilities in the U.S., delivering electricity to more than 5 million consumers in 11 states.  AEP (www.aep.com) has extensive experience building extra-high-voltage 765-kV transmission lines and owns the nation’s largest electricity transmission system, a nearly 39,000-mile network that includes 2,100 miles of 765-kV transmission lines, more than all other U.S. transmission systems combined.

MidAmerican Energy Holdings Company (www.midamerican.com), based in Des Moines, Iowa, is a global provider of energy services to more than 6.9 million customers worldwide. MidAmerican Energy Holdings Company subsidiaries, PacifiCorp and MidAmerican Energy Company, own and operate more than 18,000 miles of electric transmission lines.

---

This report made by American Electric Power and its Registrant Subsidiaries contains forward-looking statements within the meaning of Section 21E of the Securities Exchange Act of 1934. Although AEP and each of its Registrant Subsidiaries believe that their expectations are based on reasonable assumptions, any such statements may be influenced by factors that could cause actual outcomes and results to be materially different from those projected. Among the factors that could cause actual results to differ materially from those in the forward-looking statements are: the economic climate and growth in, or contraction within, AEP’s service territory and changes in market demand and demographic patterns; inflationary or deflationary interest rate trends; volatility in the financial markets, particularly developments affecting the availability of capital on reasonable terms and developments impairing AEP’s ability to finance new capital projects and refinance existing debt at attractive rates; the availability and cost of funds to finance working capital and capital needs, particularly during periods when the time lag between incurring costs and recovery is long and the costs are material; electric load and customer growth; weather conditions, including storms, and AEP’s ability to recover significant storm restoration costs through applicable rate mechanisms; available sources and costs of, and transportation for, fuels and the creditworthiness and performance of fuel suppliers and transporters; availability of necessary generating capacity and the performance of AEP’s generating plants; AEP’s ability to recover Indiana Michigan Power’s Donald C. Cook Nuclear Plant Unit 1 restoration costs through warranty, insurance and the regulatory process; AEP’s ability to recover regulatory assets and stranded costs in connection with deregulation; AEP’s ability to recover increases in fuel and other energy costs through regulated or competitive electric rates; AEP’s ability to build or acquire generating capacity, including the Turk Plant, and transmission line facilities (including the ability to obtain any necessary regulatory approvals and permits) when needed at acceptable prices and terms and to recover those costs (including the costs of projects that are cancelled) through applicable rate cases or competitive rates; new legislation, litigation and government regulation, including requirements for reduced emissions of sulfur, nitrogen, mercury, carbon, soot or particulate matter and other substances or additional regulation of fly ash and similar combustion products that could impact the continued operation and cost recovery of AEP’s plants; timing and resolution of pending and future rate cases, negotiations and other regulatory decisions (including rate or other recovery of new investments in generation, distribution and transmission service and environmental compliance); resolution of litigation (including AEP’s dispute with Bank of America); AEP’s ability to constrain operation and maintenance costs; AEP’s ability to develop and execute a strategy based on a view regarding prices of electricity, natural gas and other energy-related commodities; changes in the creditworthiness of the counterparties with whom AEP has contractual arrangements, including participants in the energy trading market; actions of rating agencies, including changes in the ratings of debt; volatility and changes in markets for electricity, natural gas, coal, nuclear fuel and other energy-related commodities; changes in utility regulation, including the implementation of electric security plans and related regulation in Ohio and the allocation of costs within regional transmission organizations, including PJM and SPP; accounting pronouncements periodically issued by accounting standard-setting bodies; the impact of volatility in the capital markets on the value of the investments held by AEP’s pension, other postretirement benefit plans and nuclear decommissioning trust and the impact on future funding requirements; prices and demand for power that AEP generates and sells at wholesale; changes in technology, particularly with respect to new, developing or alternative sources of generation; and other risks and unforeseen events, including wars, the effects of terrorism (including increased security costs), embargoes and other catastrophic events.

MEDIA CONTACT:
Larry Jones
512 391-2970 - Office
512 203-4916 - Cell Phone

More From PSO

Learn More

Manage Your Electric Bill Year-Round

Sign Up Now Pay Online for Free with Paperless Billing

Pay Online for Free with Paperless Billing

Use Online Form Report Outages On Your Mobile Phone

Report Outages On Your Mobile Phone

How We Restore Power Learn more

How We Restore Power

Visit AEP.com
Use of this site constitutes acceptance of the AEP Terms and Conditions. View our Privacy Policy. © 1996-2019 American Electric Power. All Rights Reserved.

Privacy Policy

Privacy Policy for Public Service Company of Oklahoma (PSO), a unit of American Electric Power (AEP)

Scope

This Privacy Policy applies only to PSOklahoma.com and the Public Service Company of Oklahoma customer mobile app (com.aep.customerapp.pso). Other AEP websites and apps may be governed by their own privacy policies, appropriate to the uses and needs of each. Throughout the site or app, we may provide links to resources and sites that are not part of PSOklahoma.com or the Public Service Company of Oklahoma customer mobile app. This Privacy Policy does not apply to those resources and sites.

Consent

By using this site or app, you consent to the terms of this Privacy Policy. Whenever you submit information via this site or app, you agree to the collection, use, and disclosure of that information in accordance with this Privacy Policy.

Information Collected

  1. Passively collected information

    During your use of this site or app, we may collect anonymous information about your visit here through the use of server logs, cookies, scripts, tracking pixels and other Web traffic tracking systems. This information is aggregated and used to improve user experience through analysis of user activities. This information is never combined with any of the personally identifiable information you may provide in your use of the features of this site or app.
  2. Personally identifiable information

    On certain forms of this site or app, you may be asked to provide information about yourself or your account with us, either to identify yourself to us or to request a service from us. In each case, we will inform you what information is provided at your option and what information is required to complete the transaction or activity you are engaged in. If you are unwilling to provide this required information, you will be unable to complete the requested transaction.

Use and disclosure of information

The information you provide to us will be used to respond to requests you may make for services. Some or all of this information may be added to your permanent account record and may be used for research purposes.

In addition, we may use elements of this information in the following situations:

  1. We may transfer the information to PSO’s affiliates and subsidiaries, unless such transfer is prohibited by law;
  2. We may transfer the information as part of a merger, consolidation, acquisition, divestiture or other corporate restructuring (including bankruptcy);
  3. We may make the information available to third parties who are providing the product, service or information that you have requested (but not your password);
  4. We may make such information available to third parties who are providing services to PSO (for example, providing the information to third parties performing computer-related services for PSO);
  5. We may use the information to communicate with you about products and services that may be of interest to you.
  6. We may disclose the information if we form a good-faith belief that disclosure of such information is necessary to investigate, prevent, or take action regarding any illegal activities or regarding interference with the operation of our site or violation of its terms of use; or
  7. We may disclose the information if we believe that disclosure is required by law or regulation or in response to a subpoena or other order of a court or other governmental agency.

PSO uses Flurry Analytics Service (provided by Yahoo) in order to improve its mobile apps. Flurry’s privacy policy governs the use of this information.

Also, PSO reserves the right to share any aggregated information (i.e., non-personally identifiable information) with any third parties for any reason, unless prohibited by law.

We will not sell, rent or otherwise disclose the information we gather about you or your account to any third party, except as outlined in this Privacy Policy.

Security

PSO takes reasonable steps to protect your personally identifiable information as it is transferred to us, through the use of Web technologies such as the Secure Sockets Layer and others. However, no Internet transmission of information is ever completely secure or error-free. In particular, e-mail sent to or from PSO may not be secure.

How to Reach Us

If you would like to update your personally identifiable information or if you have questions about this privacy policy, please contact us.

Changes to This Policy

PSO reserves the right to change this Privacy Policy at any time. If this Privacy Policy changes, the revised policy will be posted to this site. Please review this Privacy Policy before you provide any personally identifiable information through this site. Use of our web site after the posting of a revised privacy policy constitutes your consent to the revised policy.

This policy was last revised on December 13, 2017.

Close ×

Sign Up For Alerts

Subscribing to PSO alerts gives you instant notification for:

  • Billing & Payments - avoid late payments and disconnection
  • Outage Updates - find out if there's an outage at your address and when power will be back on

Win an Xbox One with Alerts!

Enroll in alerts to be eligible to win. Subscribing to I&M alerts gives you instant notification for:

  • Billing & Payments - avoid late payments and disconnection
  • Outage Updates - find out if there's an outage at your address and when power will be back on

Loading video...

×